August 2019

July 2019

June 2019

The earthworks and the safety measures for the construction of the excavation pit have been completed. The structural work is making good progress. The walls are currently being erected on the ground floor of the garden house. In the front building, the foundation floor has been completed.

February 2019

There are freezing temperatures outside, but construction is progressing fast. The earthworks are almost completed and the excavation pit is completed. The second crane has been set up and the foundation works of the rear building have begun. The shell will be completed in summer.

October 2018


The building permit has been granted

July 2018

Already in July 2018, the demolition of the former motor vehicle workshop began at the Wilhelmsaue 32 property. Immediately after this, the securing of the excavation was completed. The earthworks will continue until December 2018. On this 1,843-sqm site, a total of 59 apartments of between 36 and 144 sqm are being created.

x